Murlidhar Chiranjilal v. Harishchandra Dwarkadas (1962)
Supreme Court of India · AIR 1962 SC 366
Summary
The Supreme Court explained the compensatory measure of damages for breach of contract and the role of mitigation.
Facts
- The dispute concerned a seller’s failure to perform a contract for supply of goods and the resulting claim for damages.
Issues
- How are damages for non-delivery measured?
- What role does mitigation play?
Provisions involved
- Indian Contract Act, 1872 — s. 73 — Compensation for loss or damage caused by breach of contract
Reasoning
Market difference
The ordinary measure for non-delivery is the relevant difference between the contract price and market price at the date of breach, subject to proof and mitigation.
Decision
The Court applied Section 73 principles to determine the recoverable contractual loss.
Ratio decidendi
For non-delivery under a sale contract, Section 73 ordinarily uses the relevant market-price difference at breach, subject to mitigation.
Exam points
- Section 73 is compensatory.
- Mitigation limits avoidable loss.
Tags: AIBE, Judiciary, Contract, Damages